Gen Fyansford Estate

Constructors

  • Location
    Fyansford, Geelong
  • Client
    ICD Property and Project Managed through Sinclair Brook
  • Industry Sector
    Residential Sub-divisions, Land Remediation

Other Winslow Solutions involved in the project

  • Residential
  • Utilities
  • Plant and Equipment
  • Surveying
  • Traffic Management

Started in May 2018 to remediate and develop at disused Geelong quarry into a thriving 1100 lot residential neighborhood. As part of the quarry remediation more than 300,000 tonnes of rock was blasted with more than 1,000,000 tonne of rock and fill material placed. Winslow has delivered a major highway signalised intersection and over 1km of external services connecting in the new community. Recent works have included rehabilitation of ground water ponds into developed residential lots for housing.

Key Achievements

  • Started in May 2018, at a high-profile location in Geelong. To date, the value of the project is over $50 million dollars.
  • As part of the quarry rehabilitation over a 1,000,000 tonne of rock and fill placed
  • Community to have 1100 lots to be built with already 400+ lots delivered to date
  • Over 300,000 tonnes of rock blasted
  • Signalised VicRoads Intersection constructed
  • Installed and commissioned the 1st Sewer Pump Station along with significant boring works under the Moorabool River.
  • Over a 1km of large external water and gas works along the Hamilton Hwy to connect into the estate.
  • Recent works have included rehabilitation of ground water ponds into developed residential lots for housing.
  • Construction of 1km drainage outfall – in groundwater conditions.