Coomera Connector

Stage 1 South – Early Works

Infrastructure

  • Location
    Gold Coast
  • Client
    Department of Transport and Main Roads
  • Industry Sector
    Major Infrastructure

Other Winslow Solutions involved in the project

  • Major Road Projects
  • Environmental
  • Plant and Equipment
  • Surveying

Early works for Coomera Connector Stage 1 South, from Nerang River to Nerang Broadbeach road, are currently progressing and on track for completion by September 2025. Winslow's scope includes import and placement of over one million tonnes of embankment material, and preloading near to strengthen soft soils, preparing the site for the main construction phase.

Key Achievements

Key early works achievements*

  • 53,600 hours worked
  • 100% project spend with local SEQ suppliers and subcontractors
  • 340m3 concrete poured
  • 120 metres sewer installed
  • 232 metres electrical services installed
  • 100 tonnes asphalt laid for driveway access
  • 620,000 tonnes material delivered to site
  • 10469 tonnes – highest amount of material delivered to site in a single day
    *as at May 2025